Current Lead Times | |||
The following is based on actual Peachtree lighting experience within the last three months and updated accordingly. | |||
CYLINDERS Quick Ship list 8 " & 9 " & 12 " super shallow, & ultra shallow - 7 to 10 working days normal quantities All others - Aprox 6 weeks Special finishes - Aprox 8 weeks DOWNLIGHTING Housings - 7 to 10 working days normal quantities. Normal Trims - To follow in aprox 3 weeks. Turbos, Square Cones, Special Anodized finishes Trims CHURCH 500 w Quartz 30° tilt (part # PQTS-7500-M-C
other quartz - 3 to 4 weeks
Modulux series - 2 to 3 weeks Church Chandeliers - 8 to 10 weeks MEDICAL MRI Other MRI - 2 to 3 weeks Patients Exam series, Psychiatric series - 5 to 6 weeks PENDANTS / BOWLS - 5 to 8 weeks DECORATIVE Huntington Creek Sonce - 3 to 4 weeks Graphics, & Sconces - 5 to 6 weeks LED / SPECIALITY - Normally 4-8 weeks CUSTOM - Per factory quote |